This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Percent Complete, does it work?

web-app

I've added Percent Complete to the issues view and it's always blank.  I filled out time estimates for some issues and logged time against those issues and it's still blank.

Is it supposed to show logged time/estimated time?

It would be nice to see "Estimated Time" on the Log Time dialogue.  It would be even nicer to update "Estimated Time" or a "Current Estimate" while in the Log Time dialogue.

jeffrey.schoolcraft
· 1
jeffrey.schoolcraft
Replies (14)
helpful
0
not helpful

Which version of Gemini are you using? Where doesn't it show?


Saar Cohen
· 5000
Saar Cohen
helpful
0
not helpful

Gemini v2.0.5 it doesn't show on the main issues page...


jeffrey.schoolcraft
· 1
jeffrey.schoolcraft
helpful
0
not helpful

This is a BUG in 2.0.5, which will be fixed in 2.1: http://gemini.countersoft.com/Default.aspx?p=2&i=589


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Has this actually been fixed? I'm running 2.1.1, and I still witness the same issue as reported by Jeffrey...

Also, his question hasn't been answered: Is 'percentage complete' supposed to show logged time versus estimated time?

If so, it would be nice to also have a 'manual' percentage complete field, i.e. where an issue worker manually inputs how near an issue is to being resolved.


KoenR
· 1
KoenR
helpful
0
not helpful

The percent complete is a redundant field. We do not update or use it.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Redundant to what?

I also would love to have this field, but it is empty in the DB, i see that updatepercentcomplete was removed from the DB, if i were to re-add this proc, would it work? Or would it require some page changes as well?


mumbles
· 1
mumbles
helpful
0
not helpful

It is no longer updated or populated by Gemini. You could write a on update trigger to update the field.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Forgive me for asking, but why would someone remove this useful field? If you want to track a particularly large task, this percentage is vital to having management not breathing down your neck.


mumbles
· 1
mumbles
helpful
0
not helpful

This was a manually populated field that can be done via adding a custom field.


Saar Cohen
· 5000
Saar Cohen
helpful
0
not helpful

Can add logic to calculate percent complete based on estimate and logged on a custom field?


mumbles
· 1
mumbles
helpful
0
not helpful

In Gemini 3.0.4 this field still doesn't work. May you tell me, please, how  I can implement a (custom-?) field which provides the "Percent Complete"-functionality?

Best regards, Sebastian


Juuro
· 1
Juuro
helpful
0
not helpful

The percent complete field is no longer used.

Unfortunately, it is not possible to do via a custom field


Saar Cohen
· 5000
Saar Cohen
helpful
0
not helpful

[quote user="SaarCohen"]

The percent complete field is no longer used.

Unfortunately, it is not possible to do via a custom field

[/quote]
Thanks for the answer!

But... MarkWing said that this is a redundant field. But to what?


Juuro
· 1
Juuro
helpful
0
not helpful

It means that this field is no longer used.


Saar Cohen