This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Issues End date on Gantt

web-app

Issues end dates on Gantt don't reflect real end date of the issue.

For example, an issue with start date on 06 FEB 2006 and End date on 17 FEB 2006 will show on Gantt as start on 06 FEB and ending on 21 FEB, so 4 days more.  It seems that Gannt adds the 2 weekends on the graph.

Is there a parameters to adjust that calculation ?

Thanks.

Dibs
· 1
Dibs
Replies (2)
helpful
0
not helpful

Edit IssuesGantt.aspx and change the Gantt user control line to say SkipWeekends="False"

 


Harvey Kandola
· 212
Harvey Kandola
helpful
0
not helpful

Thanks, It's working fine.

Where can I find the documentation with all theses parameters and values ?