Issue in time reporting
The math in the trial gemini install I have does not appear to be working correctly.
I have a resource that has logged time for April. On a particular issue 48 hours were logged. However when running a time report only 43 are reported. You can look at the time log for the issue, due the math, and clearly see the 48 hours. It looks like the number of hours for the last day of the month is not being added in. The last day of April has 5 hours logged. And the report is being run from 4/1/2007 to 4/30/2007.
patrick24601
· 1 |
|
Monday, May 7, 2007, 6:13:56 AM |