This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Wrong order for Percent Complete column

items

Dear support,

on our Gemini 4.2.1 we observed issue with sorting item list by Percent Complete column.

For example: If I sorted items in My Work list by Percent Complete column then are items with 10 percent complete before items with 45 percent. Maybe are there items sorted as strings and not like numbers.

Screenshot attached.

Capture.PNG ]
miniMax
· 50
miniMax
Replies (2)
helpful
0
not helpful
ANSWER

This is a bug with the My Work view, it should sort ok on the filter page. It will be fixed in version 5.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Thank you


miniMax