This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Item being created with wrong status

items

When a new item is being created under the Help Desk project, the item is being created with the "In Progress" status. The Help Desk users cannot see the field from the create screen. The default status for the project is "New" yet whenever an item is created it has an initial status as "In Progress".

User94653
· 1
User94653
Replies (5)
helpful
0
not helpful

Are you assigning a resource when creating the item (or have a default one)? If so, the status will be set to the first "assigned" status.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

The user picks the resource when creating the item. I think I understand what is happening then. If the user doesn't pick a resource it is created with the "New" status. When the user picks a resource it is created with the "In Progress" status because that has the "assigned status" mark whereas "New" does not. However we want the user to pick a resource as this is the team e-mail address, but we want the item to have a "New" status until the team reviews and changes the status.


User94653
· 1
User94653
helpful
0
not helpful

Simply set the "new" status as "assigned" in the Administration -> Status page.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

If I do that, will that require every item to have a resource assigned when the status is "new"?


User94653
· 1
User94653
helpful
0
not helpful

No, that is fine.


Mark Wing
· 9108
Mark Wing