Percent complete invisible
v4.2.0 (build 3197)
Users in a certain global group cannot see or update the percent complete field when viewing or editing an issue.
They have the "Update item progress" enabled for their global group. I cannot find any "progress" checkbox in the screens section.
Only if I enable "item administration" for this group, they can see and update item progress.
What am I missing?
vashist
· 1 |
|
Thursday, October 20, 2011, 1:16:02 PM |
0
|
Please make sure that the user group is allowed to view the field in the Screen (Administration -> Screens). |
||||
|
0
|
As I said: I dont see any field in the Screens corresponding to Percent Complete or Progress. |
||||
|
0
|
Sorry, it is estimated effort. |
||||
|
0
|
Now why didn't I think of that ... Anyway, it's enabled for the global group in the edit and view stage visibility schemes. But it only shows when editing an issue, not when viewing it. |
||||
|
0
|
Please check the type of the item and make sure that you are changing the view screen for that type. Go to Administration -> Type and edit the type in question. |
||||
|
0
|
The item type is Task, and the correct visibility scheme is set. Still not showing. |
||||
|
0
|
Is it possible to send us (support at countersoft dot com) a zipped backup of your database? |
||||
|