This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Copied Test Cases - how to assign them to a Test Plan?

testing

I created a Test Plan and added a Test Case to that Test Plan.

I then opened my Test Case, copied it using the 'Copy' link and created multiple further test cases (by repeatedly copying).

None of my copied Test Cases have been assigned to my Test Plan. I cannot see them if I go to Testing -> Plans and click on my Test Plan in the left-hand folder view OR if I go to Testing -> Cases and use the filter to filter on my specific Test Plan.

I can only see the 'copied' Test Cases if I go to Testing -> Cases and do not filter on anything.

I can't see any way to assign these orphaned Test Cases to my Test Plan. I've tried opening them and clicking Amend, but do not see any way to link them to a Test Plan.

Is there any way to do this or do I have to re-create them all from scratch? I've re-looked at the Copy process and couldn't see anywhere where I could have assigned the Test Case to a Test Plan. Did I miss something?

Thanks

chrisy
· 1
chrisy
Replies (2)
helpful
0
not helpful

Yes, go to the test plan and click on the "Cases" tab (it is clicked by default). Now click on the find button to to search for your cases to assign to the plan.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Ah! Yup that worked. Suggest maybe different wording there to make it a bit more obvious. Maybe "Add Cases" or something like that!

Thanks


chrisy
· 1
chrisy