Hello,
We upgraded our Gemini server from version 3.0.3 to version 3.5.2. The upgrade went fine but know we seem to have some problems when editing issues.
We have a security scheme where project developers and project testers can edit issues and assign/re-assign issues to another user. However, since the upgrade only project administrators can see and assign/re-assign the issue assigned resource.
I have re-checked the security schemes, field visibility, etc, but the Assigned Resource field never appears when editing a issue for the mentioned project groups.
I appreciate your help in tracking this problem.
Thank you.
Marco