This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Status and Assigned values incorrect when task Moved to different Project

web-app

We are running 3.6. Say I have 2 projects with completely separate Workflows, Statuses, and Resources. When I move a task from Project 1 to Project 2, the "Status" and "Assigned To" values do not change to reflect the default choices for Project 2. This is a bit of a problem, since none of the "Status" or "Assigned To" values from Project 1 are valid in Project 2. Am I doing something wrong here?

Sean
· 1
Sean
Replies (1)
helpful
0
not helpful

Nothing wrong with what you are doing. This is an issue with the current move / copy functionality. We are looking to change that in 3.7 and make it the same as edit issue....


Mark Wing
· 9108