This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Burndown going green but status not "final"

web-app

Hi everyone,

does anyone have a good approach for having issues going green on the version page without having the issues disappear from the regular issues page?

As far as I figured out for an issue to become green on the burndown ist has to have a status that is flaged as "final" on the Issue Status admin page.

But that also means that you don't see those issues any more in the regular issue lists without removing the "exclude closed issues" flag.

So, how do we set up a status that means "almost complete but not quite finalized". Green for the burndown but still in the normal issue list for its assigned version?

Daniel

Daniel Buchholz
· 1
Daniel Buchholz
Replies (1)
helpful
0
not helpful

Green in the burndown is your backlog of issue not those that are marked as final. Those that are completed will not be shown in the burndown (from the week / day they were closed).