This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Estimated effort progress tooltip

web-app

When I enter the estimated effort for an issue and go back to view the issue there is a status bar that shows the percent complete.  When I hover over it displays a tooltip that shows the total hours estimated and the percent completed in parentheses.  The total hours appears to be the total minutes and not total hours, e.g. I entered the estimated effort as 1 hour and 0 minutes and the tooltip reads 60 hours.  Is this a bug?

I would actually just like my users to see the estimated effort, but I don't want to track time spent on an issue.  It would be nice if I could just have the time displayed instead of the progress bar but without that I need to rely on the tooltip being correct.

ESteinweg
· 1
ESteinweg
Replies (1)
helpful
0
not helpful

Yes, the tooltip label is wrong: http://gemini.countersoft.com/Default.aspx?p=2&i=1959

You can hide this for all / some of your users via the field visibility scheme (estimated effort).


Saar Cohen
· 5000