This Gemini community support site can be used to find solutions to product issues. You can log in using Open Id, Google Profile and even Facebook. Feel free to ask a question or browse FAQs and documentation. Product tour videos are also available along with how-to videos demonstrating key Gemini capabilities.




Version progress chart problem

reporting

I attach a version progress chart. In the selected version there aren't any opened items, every item is closed, but in the progress chart I see two items.

I'd like to ask it's a bug or where can I find these 2 items.

Thx.

burndown.jpg ]
hoszi
· 50
hoszi
Replies (4)
helpful
0
not helpful

There aren't any open items. You had 2 until they were closed on the 26th of Jan. The burndown will show the state of the items on the day (15th, 16th etc...).


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

It's ok, thanks. I've an other question: if you see the Version Progress Chart or the Resource Progress Chart part of the report, you will see about 75 items in this version. But if you see the burndown chart, it seems only 2 items were in this version.


hoszi
· 50
hoszi
helpful
0
not helpful
ANSWER

It is because the other items didn't have start and due date.


Mark Wing
· 9108
Mark Wing
helpful
0
not helpful

Thanks.